Work Profile Report [23W1212]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- I/176048/2023 e-file no.- 62543
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
47.53
Resanction Cost :
47.53
Tentative Cost :
36.00
Saving
11.53
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
47.53
Demand :
45.00
Allotment :
11.60
Exp in CFY :
12.61
Total Up to Date Exp :
12.61
Construction Started
Sanction on : 9 months 7 hours ago
18 Dec 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
80 %
Tentative Completion date on : 1 month 3 weeks from now
12 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 11.53 has been recorded as expected cost of work reduced from 47.53 to 36.00 . -- as on 23-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: