Work Profile Report [23W1237]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- I/123341/2023, e-file no.- 49009
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
24.06
Resanction Cost :
24.06
Tentative Cost :
23.96
Saving
0.10
Exp. Upto Last Fy :
10.15
For CFY 2025-2026
Remaining :
13.91
Demand :
8.88
Allotment :
8.98
Exp in CFY :
8.88
Total Up to Date Exp :
19.03
Survey work done
Sanction on : 2 years 7 months ago
19 May 2023
Physical Progress:
At start of FY 2025-2026 :
50 %
Up to Date :
70 %
Tentative Completion date on : 2 months 4 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 0.1 has been recorded as expected cost of work reduced from 24.06 to 23.96 . -- as on 02-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: