Work Profile Report [23W1241]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- I/238170/2024, e-file no.- 70037
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
42.37
Resanction Cost :
42.37
Tentative Cost :
42.27
Saving
0.10
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
42.27
Demand :
40.07
Allotment :
22.65
Exp in CFY :
22.65
Total Up to Date Exp :
22.75
Work completed
Sanction on : 1 year 4 months ago
06 Sep 2024
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
100 %
Tentative Completion date on : 6 months 3 weeks ago
30 Jun 2025
Actual Completion Date : 4 months 2 weeks ago
04 Sep 2025
Physical Linear Components
Remark
निविदा कम दरों में प्राप्त होने के कारण कार्य में बचत हो रही है, कार्य पूर्ण I -- as on 15-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2026 PWD Uttarakhand