Work Profile Report [23W1257]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : G.O. no.- I/252714/2024, e-file no.- 49971
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
66.08
Resanction Cost :
66.08
Tentative Cost :
65.98
Saving
0.10
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
65.98
Demand :
48.57
Allotment :
13.67
Exp in CFY :
13.67
Total Up to Date Exp :
13.77
Construction Started
Sanction on : 1 year 2 months ago
11 Nov 2024
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
40 %
Tentative Completion date on : 9 months 6 days from now
30 Oct 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
इण्टरलाॅकिंग का कार्य प्रगति पर। -- as on 15-Jan-2026
Assets :
Work not linked with IM