Work Profile Report [23W1265]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- I/252714/2024, e-file no.- 49971
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
36.70
Resanction Cost :
36.70
Tentative Cost :
36.70
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
36.60
Demand :
36.60
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
Construction Started
Sanction on : 6 months 2 days ago
11 Nov 2024
Physical Progress:
At start of FY 2025-2026 :
75 %
Up to Date :
75 %
Tentative Completion date on : 1 month 2 weeks from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 15-Feb-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: