Work Profile Report [23W1279]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- I/270868/2025, e-file no.- 49971
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
82.13
Resanction Cost :
82.13
Tentative Cost :
82.13
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
82.03
Demand :
82.03
Allotment :
72.78
Exp in CFY :
72.78
Total Up to Date Exp :
72.88
Construction Started
Sanction on : 10 months 2 weeks ago
27 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
75 %
Tentative Completion date on : 1 week 3 days from now
27 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर -- as on 28-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: