Work Profile Report [23W926]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 सं0 - 739/111(2) /17 - 66 (एम0एल0ए0)/17, दिनांक 20-06-2017
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
129.80
Resanction Cost :
129.80
Tentative Cost :
129.80
Exp. Upto Last Fy :
118.94
For CFY 2024-2025
Remaining :
10.86
Demand :
10.86
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
118.94
Work completed
Sanction on : 7 years 6 months ago
20 Jun 2017
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 years 2 months ago
01 Oct 2020
Actual Completion Date : 4 years 5 months ago
01 Jul 2020
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 14-Dec-2022
Assets :
Work not linked with IM
Bridges on The Basis of AI: