Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 1.500 | 0 | 0.000 | 0.000 |
23W926 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 - 739/111(2) /17 - 66 (एम0एल0ए0)/17, दिनांक 20-06-2017
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
129.80
Resanction Cost :
129.80
Tentative Cost :
129.80
Exp. Upto Last Fy : 118.94
For CFY 2024-2025
Remaining : 10.86
Demand : 10.86
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 118.94
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
7 years 3 weeks ago
20 Jun 2017
Tentative Completion date:
3 years 9 months ago
01 Oct 2020
Actual Completion Date:
4 years 2 weeks ago
01 Jul 2020
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 14-Dec-2022