Work Profile Report [23W968]
Fin Plan
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.सं. 1210/।।।(2)/ 19-67 (एम.एल.ए.)/2017 टी0सी0 दि0 05-03-2019
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
157.07
Resanction Cost :
157.07
Tentative Cost :
157.07
Exp. Upto Last Fy :
38.71
For CFY 2024-2025
Remaining :
118.36
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
38.71
Construction Started
Sanction on : 5 years 8 months ago
05 Mar 2019
Physical Progress:
At start of FY 2024-2025 :
30 %
Up to Date :
100 %
Tentative Completion date on : 3 years 8 months ago
01 Mar 2021
Actual Completion Date : 2 years 3 months ago
14 Aug 2022
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 13-Dec-2022
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: RCC Slabe Bridge at GIC Back Side Near Majar Over Local Nala
© PWD Uttarakhand