Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
Closed Work 23W968 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: RCC Slabe Bridge at GIC Back Side Near Majar Over Local Nala
Administrative Approval Detail : शा.सं. 1210/।।।(2)/ 19-67 (एम.एल.ए.)/2017 टी0सी0 दि0 05-03-2019
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
157.07
Resanction Cost :
157.07
Tentative Cost :
157.07
Exp. Upto Last Fy : 38.71
For CFY 2024-2025
Remaining : 118.36
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 38.71
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 100 %
Sanction on :
5 years 4 months ago
05 Mar 2019
Tentative Completion date:
3 years 4 months ago
01 Mar 2021
Actual Completion Date:
1 year 11 months ago
14 Aug 2022
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 13-Dec-2022
Physical Peramenters