Work Profile Report [23W989]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या 4592/।।।(2)/19-66 (एम0एल0ए0)/17 दिनांक 27-12-2019
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
24.81
Resanction Cost :
24.81
Tentative Cost :
24.81
Exp. Upto Last Fy :
23.08
For CFY 2025-2026
Remaining :
1.73
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
23.08
Work completed
Sanction on : 5 years 6 months ago
27 Dec 2019
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 years 8 months ago
31 Oct 2020
Actual Completion Date : 2 years 7 months ago
15 Nov 2022
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 14-Dec-2022
Assets :
Work not linked with IM
Bridges on The Basis of AI: