Work Profile Report [24W1071]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिलाधिकारी उधमसिंह नगर के पत्रांक-545ध्जि0यो0-35ध्वि0प्रशा0स्वी0ध्लो0नि0वि0ध्25-26 दिनांक-05-07-2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
15.00
Resanction Cost :
15.00
Tentative Cost :
15.00
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
15.00
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 6 months 2 weeks ago
05 Jul 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
30 %
Tentative Completion date on : 2 months 6 days from now
30 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
तटबन्ध व जी0एस0बी0 का कार्य प्रगति पर है। -- as on 22-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: