Administrative Approval Detail : G.O No. I/327110/2025, Dated: 02.09.2025, Sanction Rs. 203.85 Lakh, E File No. 46429
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
203.85
Resanction Cost :
203.85
Tentative Cost :
203.85
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
203.85
Demand :
48.90
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 2 months 2 weeks ago
02 Sep 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
20 %
Tentative Completion date on : 7 months 2 weeks from now
08 Jul 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
तटबन्ध का कार्य 50 प्रतिशत पूर्ण। -- as on 22-Nov-2025
Assets :
Work not linked with IM