Work Profile Report [24W730]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या 293/।।।(2)/19-70(एम0एल0ए0)/2017 टी0सी0 दिनांक 17-01-2020
TS Amount (lakhs) : 143.06 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
143.06
Resanction Cost :
128.92
Tentative Cost :
128.92
Exp. Upto Last Fy :
118.60
For CFY 2025-2026
Remaining :
10.32
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
118.60
In Maintenance After Completion
Sanction on : 5 years 11 months ago
17 Jan 2020
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 9 months ago
31 Mar 2023
Actual Completion Date : 2 years 9 months ago
28 Mar 2023
Physical Linear Components
Remark
Overall Saving 14.14 has been recorded as expected cost of work reduced from 143.06 to 128.92 . -- as on 18-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: