Work Profile Report [24W731]
Tenders
Project Activities
Documents
Samples
Administrative Approval Detail : शासनदेश संख्या 616(1)/।।।(2)/20-68(एम0एल0ए0)/2017 दिनांक 07-02-2020
TS Amount (lakhs) : 2490.31 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
2490.31
Resanction Cost :
2490.31
Tentative Cost :
2490.31
Exp. Upto Last Fy :
2,424.98
For CFY 2025-2026
Remaining :
65.33
Demand :
55.00
Allotment :
52.96
Exp in CFY :
52.96
Total Up to Date Exp :
2,477.94
In Maintenance After Completion
Sanction on : 5 years 10 months ago
07 Feb 2020
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 years 7 months ago
31 May 2022
Actual Completion Date : 4 years 6 months ago
30 Jun 2021
Physical Linear Components
Remark
पी0सी0आर0 प्रेषित की जा रही है। मार्च - 2026 को कार्य एम0आई0एस0 से हटा दिया जायेगा। -- as on 27-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: