Work Profile Report : 24W756
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश संख्या 136/।।।(2)/20-29(प्रा0आ0) /2018 दिनांक 01-02-2021
TS Amount (lakhs) : 581.01 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
581.04
Resanction Cost :
581.04
Tentative Cost :
581.04
Exp. Upto Last Fy :
33.51
For CFY 2025-2026
Remaining :
547.53
Demand :
321.18
Allotment :
133.35
Exp in CFY :
99.83
Total Up to Date Exp :
133.34
Construction Started
Sanction on : 5 years 1 week ago
01 Feb 2021
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
40 %
Tentative Completion date on : 10 months 2 weeks from now
31 Dec 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पीयर्स एवं एबटमेन्ट का कार्य 75 प्रतिशत पूर्ण। शेष कार्य प्रगति पर है। -- as on 30-Jan-2026