Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.2 | 3.2 | 3.2 | 0 |
Closed Work 24W813 :
Administrative Approval Detail : GO No- 5689/III(2)/21-70(MLA)/2017 Date 24-11-2021
TS Amount (lakhs) : 80.94 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
80.94
Resanction Cost :
80.94
Tentative Cost :
80.94
Exp. Upto Last Fy : 73.20
For CFY 2024-2025
Remaining : 7.74
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 73.20
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 85 %
Sanction on :
2 years 7 months ago
24 Nov 2021
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पटरी हेतु मिट्टी पूर्ण जी0एस0बी0 कार्य पूर्ण। 2.00 कि0मी0 लम्बाई में पी0सी0 का कार्य पूर्ण। -- as on 01-Sep-2022
Physical Peramenters