Work Profile Report [24W813]
Fin Plan
Remarks
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : GO No- 5689/III(2)/21-70(MLA)/2017 Date 24-11-2021
TS Amount (lakhs) : 80.94 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
80.94
Resanction Cost :
80.94
Tentative Cost :
80.94
Exp. Upto Last Fy :
73.20
For CFY 2024-2025
Remaining :
7.74
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
73.20
Construction Started
Sanction on : 3 years 1 month ago
24 Nov 2021
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
85 %
Tentative Completion date on : 1 year 8 months ago
31 Mar 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पटरी हेतु मिट्टी पूर्ण जी0एस0बी0 कार्य पूर्ण। 2.00 कि0मी0 लम्बाई में पी0सी0 का कार्य पूर्ण। -- as on 01-Sep-2022