Length of Road [Km] | 24.91 | 24.91 | 24.91 | 0 |
Closed Work 24W838 :
Administrative Approval Detail : GO No- 6173/III(2)/21-70(MLA)/2017 TC 5 Date 22-12-2021
TS Amount (lakhs) : 964.2 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
964.20
Resanction Cost :
964.20
Tentative Cost :
964.20
Exp. Upto Last Fy : 963.23
For CFY 2024-2025
Remaining : 0.97
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 963.23
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
2 years 6 months ago
22 Dec 2021
Tentative Completion date:
2 years 3 weeks ago
20 Jun 2022
Actual Completion Date:
1 year 11 months ago
06 Aug 2022
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 01-Sep-2022