Work Profile Report [24W932]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-938/अठारह-बी-1/23-04(88)/2023 दि0 07-07-2023
TS Amount (lakhs) : 37.53 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
37.53
Resanction Cost :
37.53
Tentative Cost :
37.53
Exp. Upto Last Fy :
37.02
For CFY 2025-2026
Remaining :
0.51
Demand :
0.00
Allotment :
13.11
Exp in CFY :
0.00
Total Up to Date Exp :
37.02
Work completed
Sanction on : 2 years 2 days ago
07 Jul 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 3 months ago
30 Mar 2024
Actual Completion Date : 1 year 1 week ago
28 Jun 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 10-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand