Work Profile Report [24W934]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : ई-फाईल संख्या 58805 दि0 24-08-2023
TS Amount (lakhs) : 84.66 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
84.66
Resanction Cost :
84.66
Tentative Cost :
84.66
Exp. Upto Last Fy :
35.50
For CFY 2024-2025
Remaining :
49.16
Demand :
57.04
Allotment :
35.01
Exp in CFY :
17.71
Total Up to Date Exp :
53.21
Construction Started
Sanction on : 11 months 3 weeks ago
25 Aug 2023
Physical Progress:
At start of FY 2024-2025 :
85 %
Up to Date :
95 %
Tentative Completion date on : 3 weeks 2 days ago
24 Jul 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी0सी0 पूर्ण पटरी प्रगति में। -- as on 10-May-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: