Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.2 | 0.2 | 0.100 | 0.1 | 0.100 | 0.000 |
24W941 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई-फाईल संख्या - 55798- दि0 20-07-2023
TS Amount (lakhs) : 38.52 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
38.52
Resanction Cost :
38.52
Tentative Cost :
38.52
Exp. Upto Last Fy : 2.03
For CFY 2024-2025
Remaining : 36.49
Demand : 36.49
Allotment : 20.00
Exp in CFY : 12.71
Total Up to Date Exp : 14.74
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 76 %
Sanction on :
11 months 3 weeks ago
20 Jul 2023
Tentative Completion date:
1 month 1 week from now
30 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मिट्टी एवं जी0एस0बी0 का कार्य पूर्ण। इन्टर कोट का कार्य प्रगति में। -- as on 03-Jan-2024
Physical Peramenters