Work Profile Report [24W952]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई0फाईल संख्या 58769 दि0 22-11-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
218.13
Resanction Cost :
218.13
Tentative Cost :
180.00
Saving
38.13
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
218.03
Demand :
218.03
Allotment :
111.02
Exp in CFY :
130.59
Total Up to Date Exp :
130.69
Construction Started
Sanction on : 1 year 1 day ago
22 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
35 %
Up to Date :
80 %
Tentative Completion date on : 3 months 3 weeks from now
15 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी-3 पूर्ण, पी0सी0 3.50 कि0मी0 पूर्ण, शेष र्का प्रगति पर है। -- as on 05-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: