Work Profile Report [24W954]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई0फाईल संख्या 58769 दि0 22-11-2023
TS Amount (lakhs) : 96.29 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
96.29
Resanction Cost :
96.29
Tentative Cost :
96.29
Exp. Upto Last Fy :
40.47
For CFY 2024-2025
Remaining :
55.82
Demand :
64.25
Allotment :
55.82
Exp in CFY :
51.17
Total Up to Date Exp :
91.64
Work completed
Sanction on : 1 year 1 month ago
22 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
35 %
Up to Date :
100 %
Tentative Completion date on : 7 months 1 week ago
18 May 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 27-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand