Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.2 | 1.2 | 0.500 | 0.7 | 0.700 | 0.000 |
24W958 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई0फाईल संख्या 59975 दि0 24-11-2023
TS Amount (lakhs) : 35.63 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
35.63
Resanction Cost :
35.63
Tentative Cost :
35.63
Exp. Upto Last Fy : 18.42
For CFY 2024-2025
Remaining : 17.21
Demand : 17.21
Allotment : 10.00
Exp in CFY : 0.00
Total Up to Date Exp : 18.42
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 80 %
Sanction on :
7 months 3 weeks ago
24 Nov 2023
Tentative Completion date:
4 weeks 16 hours from now
15 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 प्रगति पर है। -- as on 16-May-2024
Physical Peramenters