Work Profile Report [24W959]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई0फाईल संख्या 59975 दि0 24-11-2023
TS Amount (lakhs) : 79.38 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
79.38
Resanction Cost :
79.38
Tentative Cost :
79.38
Exp. Upto Last Fy :
67.96
For CFY 2024-2025
Remaining :
11.42
Demand :
19.28
Allotment :
17.07
Exp in CFY :
8.12
Total Up to Date Exp :
76.08
Work completed
Sanction on : 11 months 4 weeks ago
24 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 3 months 1 week ago
15 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 10-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: