Work Profile Report [24W960]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई0फाईल संख्या 59975 दि0 24-11-2023
TS Amount (lakhs) : 42.97 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
42.97
Resanction Cost :
42.97
Tentative Cost :
42.97
Exp. Upto Last Fy :
12.70
For CFY 2024-2025
Remaining :
30.27
Demand :
27.86
Allotment :
16.13
Exp in CFY :
18.53
Total Up to Date Exp :
31.24
Work completed
Sanction on : 1 year 1 month ago
24 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 2 months 1 week ago
15 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 29-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand