Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 2.000 | 0.000 |
24W961 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई0फाईल संख्या 59975 दि0 24-11-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
44.65
Resanction Cost :
44.65
Tentative Cost :
44.65
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 44.65
Demand : 44.65
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 15 %
Sanction on :
7 months 3 weeks ago
24 Nov 2023
Tentative Completion date:
2 months 4 weeks from now
15 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी-3 का कार्य प्रगति में। -- as on 29-Jun-2024
Physical Peramenters