Work Profile Report [24W962]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : शासनादेश ई0फाईल संख्या 59975 दि0 24-11-2023
TS Amount (lakhs) : 68.39 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
68.39
Resanction Cost :
68.39
Tentative Cost :
68.39
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
68.39
Demand :
68.39
Allotment :
30.00
Exp in CFY :
20.49
Total Up to Date Exp :
20.49
Construction Started
Sanction on : 8 months 3 weeks ago
24 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
5 %
Up to Date :
50 %
Tentative Completion date on : 1 day 1 hour ago
15 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी- 3 का कार्य प्रगति पर है। -- as on 16-May-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: