Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.25 | 1.25 | 0.000 | 1.25 | 1.250 | 0.000 |
24W970 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : DM Udham singh Order No. 1539/Jila Yojana-35/Finencial administration/ P.W.D/2023-24
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
40.00
Resanction Cost :
40.00
Tentative Cost :
40.00
Exp. Upto Last Fy : 3.36
For CFY 2024-2025
Remaining : 36.64
Demand : 36.64
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 3.36
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 80 %
Sanction on :
7 months 4 days ago
13 Dec 2023
Tentative Completion date:
2 months 4 weeks from now
15 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी-3 का कार्य पूर्ण। -- as on 29-Jun-2024
Physical Peramenters