Work Profile Report [24W970]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : DM Udham singh Order No. 1539/Jila Yojana-35/Finencial administration/ P.W.D/2023-24
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
40.00
Resanction Cost :
40.00
Tentative Cost :
40.00
Exp. Upto Last Fy :
3.36
For CFY 2024-2025
Remaining :
36.64
Demand :
36.64
Allotment :
16.31
Exp in CFY :
16.31
Total Up to Date Exp :
19.67
Construction Started
Sanction on : 11 months 1 week ago
13 Dec 2023
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
80 %
Tentative Completion date on : 3 months 3 weeks from now
15 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी-3 का कार्य पूर्ण। पी0सी0 प्रगति में है। -- as on 11-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: