Work Profile Report [25W1108]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 । /106915 /2023 (ई0 फाईल सं0 48224) दि0 16.3.23
TS Amount (lakhs) : 698.12 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
698.12
Resanction Cost :
698.12
Tentative Cost :
650.00
Saving
48.12
Exp. Upto Last Fy :
565.32
For CFY 2024-2025
Remaining :
132.80
Demand :
87.00
Allotment :
84.87
Exp in CFY :
84.87
Total Up to Date Exp :
650.20
Work completed
Sanction on : 1 year 9 months ago
16 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 8 months ago
19 Apr 2023
Actual Completion Date : 1 year 8 months ago
30 Mar 2023
Physical Linear Components
Remark
कार्य पूर्ण -- as on 25-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: