Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.85 | 1.85 | 0.000 | 1.85 | 1.850 | 0.000 |
25W1126 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /10569 /2023 (ई0 फाईल सं0 50224) दि0 28.3.23
TS Amount (lakhs) : 83.15 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
83.15
Resanction Cost :
83.15
Tentative Cost :
83.15
Exp. Upto Last Fy : 15.33
For CFY 2024-2025
Remaining : 67.82
Demand : 35.00
Allotment : 25.00
Exp in CFY : 13.33
Total Up to Date Exp : 28.67
Work completed
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
28 Mar 2023
Tentative Completion date:
2 weeks 3 days ago
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 27-Jun-2024
Physical Peramenters