Administrative Approval Detail : शा0सं0 । /111699 /2023 (ई0 फाईल सं0 47605) दि0 31.3.23
TS Amount (lakhs) : 89.9 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
89.90
Resanction Cost :
89.90
Tentative Cost :
87.50
Saving
2.40
Exp. Upto Last Fy :
72.57
For CFY 2024-2025
Remaining :
17.33
Demand :
16.00
Allotment :
16.00
Exp in CFY :
13.06
Total Up to Date Exp :
85.64
Work completed
Sanction on : 1 year 8 months ago
31 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
100 %
Tentative Completion date on : 9 months 1 week ago
16 Mar 2024
Actual Completion Date : 9 months 1 week ago
14 Mar 2024
Physical Linear Components
Remark
कार्य पूर्ण -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: