Work Profile Report [25W1141]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शा0सं0 । /38893 /2023 (ई0 फाईल सं0 54118) दि0 19.07.2023
TS Amount (lakhs) : 94.15 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
94.15
Resanction Cost :
94.15
Tentative Cost :
79.50
Saving
14.65
Exp. Upto Last Fy :
64.64
For CFY 2024-2025
Remaining :
29.51
Demand :
22.00
Allotment :
20.00
Exp in CFY :
19.47
Total Up to Date Exp :
84.10
Work completed
Sanction on : 1 year 4 weeks ago
19 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
76 %
Up to Date :
100 %
Tentative Completion date on : 4 months 1 week ago
09 Apr 2024
Actual Completion Date : 4 months 1 week ago
09 Apr 2024
Physical Linear Components
Remark
Overall Saving 14.65 has been recorded as expected cost of work reduced from 94.15 to 79.5 . -- as on 30-Jul-2024
Assets :
Work not linked with IM