Work Profile Report [25W1153]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 । /42056 /2023 (ई0 फाईल सं0 50220) दि0 31.07.2023
TS Amount (lakhs) : 176.22 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
176.22
Resanction Cost :
176.22
Tentative Cost :
172.50
Saving
3.72
Exp. Upto Last Fy :
144.69
For CFY 2024-2025
Remaining :
31.53
Demand :
30.00
Allotment :
31.00
Exp in CFY :
13.66
Total Up to Date Exp :
158.35
Construction Started
Sanction on : 1 year 3 months ago
31 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
90 %
Tentative Completion date on : 1 month 2 days from now
30 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3.40 किमी0 लम्बाई में पी0सी0 का कार्य पूर्ण, शेष कार्य प्रगति में। -- as on 24-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: