Work Profile Report [25W1154]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 । /164733 /2023 (ई0 फाईल सं0 47605) दि0 27.10.2023
TS Amount (lakhs) : 99.16 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
99.16
Resanction Cost :
99.16
Tentative Cost :
65.00
Saving
34.16
Exp. Upto Last Fy :
0.19
For CFY 2024-2025
Remaining :
98.97
Demand :
50.00
Allotment :
34.29
Exp in CFY :
53.57
Total Up to Date Exp :
53.76
Construction Started
Sanction on : 1 year 3 weeks ago
27 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
75 %
Tentative Completion date on : 2 weeks 1 day from now
09 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.65 किमी0 लम्बाई में कार्य पूर्ण, शेष कार्य प्रगति में। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand