Work Profile Report [25W1156]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 । /167915 /2023 (ई0 फाईल सं0 56071) दि0 09.11.2023
TS Amount (lakhs) : 104.26 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
104.26
Resanction Cost :
104.26
Tentative Cost :
96.50
Saving
7.76
Exp. Upto Last Fy :
83.32
For CFY 2024-2025
Remaining :
20.94
Demand :
20.00
Allotment :
20.85
Exp in CFY :
20.85
Total Up to Date Exp :
104.17
Work completed
Sanction on : 1 year 2 weeks ago
09 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
76 %
Up to Date :
100 %
Tentative Completion date on : 1 month 1 week ago
10 Oct 2024
Actual Completion Date : 7 months 3 days ago
20 Apr 2024
Physical Linear Components
Remark
कार्य पूर्ण -- as on 24-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand