Work Profile Report [25W1159]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : कार्यालय जिलाधिकारी ऊधमसिंहनगर का पत्रांक 1550/जि0यो0-35/वि0प्रशा0स्वी0/लो0नि0वि0/2023-24 दि0 15.12.2023
TS Amount (lakhs) : 25 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
25.00
Resanction Cost :
25.00
Tentative Cost :
25.00
Exp. Upto Last Fy :
5.00
For CFY 2024-2025
Remaining :
20.00
Demand :
15.00
Allotment :
10.00
Exp in CFY :
19.43
Total Up to Date Exp :
24.43
Work completed
Sanction on : 11 months 1 week ago
15 Dec 2023
Physical Progress:
At start of FY 2024-2025 :
60 %
Up to Date :
100 %
Tentative Completion date on : 3 months 2 weeks ago
06 Aug 2024
Actual Completion Date : 3 months 2 weeks ago
06 Aug 2024
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष -- as on 24-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand