Work Profile Report [25W1161]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : कार्यालय जिलाधिकारी ऊधमसिंहनगर का पत्रांक 1558/जि0यो0/अनु0संशोधन/2023-24 दि0 15.12.2023
TS Amount (lakhs) : 24 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
24.00
Resanction Cost :
24.00
Tentative Cost :
24.00
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
24.00
Demand :
18.00
Allotment :
16.00
Exp in CFY :
15.84
Total Up to Date Exp :
15.84
Construction Started
Sanction on : 8 months 1 day ago
15 Dec 2023
Physical Progress:
At start of FY 2024-2025 :
60 %
Up to Date :
75 %
Tentative Completion date on : 2 weeks 3 days ago
30 Jul 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
टाप कोट का कार्य पूर्ण, शेष कार्य प्रगति में -- as on 27-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: