Work Profile Report [25W1164]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : कार्यालय जिलाधिकारी ऊधमसिंहनगर का पत्रांक 1550/जि0यो0-35/वि0प्रशा0स्वी0/लो0नि0वि0/2023-24 दि0 15.12.2023
TS Amount (lakhs) : 25 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
25.00
Resanction Cost :
25.00
Tentative Cost :
25.00
Exp. Upto Last Fy :
9.43
For CFY 2024-2025
Remaining :
15.57
Demand :
12.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
9.43
Construction Started
Sanction on : 8 months 1 day ago
15 Dec 2023
Physical Progress:
At start of FY 2024-2025 :
85 %
Up to Date :
90 %
Tentative Completion date on : 3 days 22 hours from now
20 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
200 मी0 लम्बाई में कार्य पूर्ण, शेष कार्य प्रगति में। -- as on 27-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: