Work Profile Report [25W1171]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 । /181012 /2024 (ई0 फाईल सं0 56071) दि0 10.01.2024
TS Amount (lakhs) : 71.5 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
71.50
Resanction Cost :
71.50
Tentative Cost :
50.00
Saving
21.50
Exp. Upto Last Fy :
0.07
For CFY 2024-2025
Remaining :
71.43
Demand :
40.00
Allotment :
5.00
Exp in CFY :
14.27
Total Up to Date Exp :
14.34
Construction Started
Sanction on : 8 months 1 week ago
10 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
30 %
Up to Date :
70 %
Tentative Completion date on : 2 weeks 1 day from now
04 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
टाप कोट का कार्य पूर्ण, शेष कार्य प्रगति में। -- as on 24-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand