Administrative Approval Detail : शा0सं0 । /184680 /2024 (ई0 फाईल सं0 54118) दि0 24.01.2024
TS Amount (lakhs) : 189.66 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
189.66
Resanction Cost :
189.66
Tentative Cost :
60.00
Saving
129.66
Exp. Upto Last Fy :
0.19
For CFY 2024-2025
Remaining :
189.47
Demand :
180.00
Allotment :
75.00
Exp in CFY :
66.91
Total Up to Date Exp :
67.10
Construction Started
Sanction on : 11 months 1 day ago
24 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
70 %
Tentative Completion date on : 5 months 1 week from now
06 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
टाप कोट का कार्य प्रगति में -- as on 29-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: