Work Profile Report [25W1180]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : शा0सं0 । /197584 /2024 (ई0 फाईल सं0 47605) दि0 12.03.2024
TS Amount (lakhs) : 62.45 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
62.45
Resanction Cost :
62.45
Tentative Cost :
43.00
Saving
19.45
Exp. Upto Last Fy :
0.07
For CFY 2024-2025
Remaining :
62.38
Demand :
30.00
Allotment :
10.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.07
Construction Started
Sanction on : 5 months 4 days ago
12 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
5 %
Tentative Completion date on : 7 months 3 weeks from now
09 Apr 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 19.45 has been recorded as expected cost of work reduced from 62.45 to 43 . -- as on 30-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: