Work Profile Report [25W1182]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 । /196330 /2024 (ई0 फाईल सं0 68062) दि0 06.03.2024
TS Amount (lakhs) : 36.3 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
36.30
Resanction Cost :
36.30
Tentative Cost :
36.00
Saving
0.30
Exp. Upto Last Fy :
0.08
For CFY 2024-2025
Remaining :
36.22
Demand :
25.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.08
Construction Started
Sanction on : 6 months 1 week ago
06 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
5 %
Tentative Completion date on : 3 months 2 weeks from now
03 Jan 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मिटटी द्वारा तटबंध निर्माण का कार्य प्रगति में। -- as on 24-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: