Work Profile Report [25W1183]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : शा0सं0 ।/198898/2024 (ई0 फाईल सं0- 68208) दि0 14.03.2024
TS Amount (lakhs) : 189.7 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
189.70
Resanction Cost :
189.70
Tentative Cost :
50.00
Saving
139.70
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
189.60
Demand :
140.00
Allotment :
5.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
in Tendering Stage
Sanction on : 5 months 2 days ago
14 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on : 10 months 1 week from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 139.7 has been recorded as expected cost of work reduced from 189.7 to 50 . -- as on 30-Jul-2024