Work Profile Report [25W1206]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 ।/258813/2024 (ई0 फाईल सं0 66722) दि0 05.12.2024
TS Amount (lakhs) : 53.9 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
53.90
Resanction Cost :
53.90
Tentative Cost :
53.90
Exp. Upto Last Fy :
21.34
For CFY 2025-2026
Remaining :
32.56
Demand :
32.00
Allotment :
31.78
Exp in CFY :
31.78
Total Up to Date Exp :
53.12
Work completed
Sanction on : 7 months 1 week ago
05 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
100 %
Tentative Completion date on : 1 month 2 weeks ago
30 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण -- as on 01-Jul-2025
Assets :
Work not linked with IM