Administrative Approval Detail : शा0सं0 ।/270809/2025 (ई0 फाईल सं0 29156) दि0 27.01.2025
TS Amount (lakhs) : 92.68 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
92.68
Resanction Cost :
92.68
Tentative Cost :
92.68
Exp. Upto Last Fy :
0.09
For CFY 2025-2026
Remaining :
92.59
Demand :
75.00
Allotment :
12.92
Exp in CFY :
12.92
Total Up to Date Exp :
13.00
Construction Started
Sanction on : 8 months 3 days ago
27 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
70 %
Tentative Completion date on : 1 month 3 weeks from now
27 Nov 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
टाप कोट का कार्य पूर्ण, शेष कार्य प्रगति में -- as on 30-Sep-2025