Work Profile Report [25W1215]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 ।/283314/2025 (ई0 फाईल सं0 47605) दि0 18.03.2025
TS Amount (lakhs) : 73.27 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
73.27
Resanction Cost :
73.27
Tentative Cost :
73.27
Exp. Upto Last Fy :
0.09
For CFY 2025-2026
Remaining :
73.18
Demand :
65.00
Allotment :
62.64
Exp in CFY :
62.64
Total Up to Date Exp :
62.73
Construction Started
Sanction on : 6 months 1 week ago
18 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
90 %
Tentative Completion date on : 1 month 1 week from now
08 Nov 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
टाईल्स का कार्य पूर्ण, शेष कार्य प्रगति में -- as on 30-Sep-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: