Work Profile Report : 25W1226
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 ।/292421/2025 (ई0 फाईल सं0 54118) दि0 25.04.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
161.22
Resanction Cost :
161.22
Tentative Cost :
161.22
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
161.22
Demand :
51.00
Allotment :
63.39
Exp in CFY :
63.39
Total Up to Date Exp :
63.39
Construction Started
Sanction on : 10 months 1 week ago
25 Apr 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
60 %
Tentative Completion date on : 3 months 3 weeks from now
30 Jun 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
टाप कोट का कार्य पूर्ण, शेष कार्य प्रगति में -- as on 02-Mar-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: