Work Profile Report [2W20]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 3241(1)/।।।(2)/12-02(मु.मं.घो.)/2012 दिनांक 11.09.2012
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
50.40
Resanction Cost :
50.40
Tentative Cost :
2.06
Saving
48.34
Exp. Upto Last Fy :
2.06
For CFY 2025-2026
Remaining :
48.34
Demand :
0.00
Allotment :
3.76
Exp in CFY :
3.76
Total Up to Date Exp :
5.82
Work completed
Sanction on : 12 years 10 months ago
11 Sep 2012
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 4 months ago
31 Mar 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अमल-दरामद की कार्यवाही गतिमान। -- as on 25-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: