Work Profile Report [2W208]

मु.मं.घो.सं0 811/2014 के अन्तर्गत नैनी से क्वेराली तक मोटर मार्ग का नव निर्माण कार्य (प्रथम चरण)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 1935/।।।(2)/15-03(मु.मं.घो.)/2015 दि0 26.3.2015

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

30.98

Resanction Cost :

30.98

Tentative Cost :

0.03

Saving

30.95

Exp. Upto Last Fy :

0.03

For CFY 2025-2026

Remaining :

30.95

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.03

Alignment Approved

Sanction on : 10 years 4 months ago

26 Mar 2015

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

0 %

Tentative Completion date on : 3 weeks 5 days from now

31 Aug 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
4
4
4
-

Remark

view all

वर्तमान में प्रस्ताव आनलाईन भारत सरकार स्तर पर -- as on 25-Dec-2024

Rating : 0

Forest Case Pending At : 12: AIP DM

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: