Work Profile Report [2W211]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.सं. 4520/।।।(2)/15-08(मु0मं0घो0)/15 दि0 19.6.15
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
29.42
Resanction Cost :
29.42
Tentative Cost :
0.10
Saving
29.32
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
29.32
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
Alignment Approved
Sanction on : 10 years 1 month ago
19 Jun 2015
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 4 days 16 hours ago
31 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वर्तमान में क्षतिपूरक वृक्षारोपण हेतु भूमि आवेदित की गयी है। -- as on 17-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: