Work Profile Report [2W25]

मकड़ाऊ-दशौला मोटर मार्ग (किमी. 1-5)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 2120/।।।(2)/16-08(प्रा.आ.)/2004टी.सी. दि0 11-07-2016

TS Amount (lakhs) : 155.98 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

155.98

Resanction Cost :

155.98

Tentative Cost :

155.98

Exp. Upto Last Fy :

85.80

For CFY 2025-2026

Remaining :

70.18

Demand :

4.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

85.80

Construction Started

Sanction on : 9 years 4 weeks ago

11 Jul 2016

Physical Progress:

At start of FY 2025-2026 :

78 %

Up to Date :

78 %

Tentative Completion date on : 11 months 1 week ago

31 Aug 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
5
5
5
-

Remark

view all

3.50 किमी0 मार्ग यातायात हेतु उपलब्ध है। शेष 1.50 किमी0 में पहाड़ कटान कार्य पूर्ण। स्कपर निर्माण कार्य प्रगति में। -- as on 10-Nov-2023

Rating : 78

Forest Case Pending At : 13: AIP DFO

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: